Helen Street and Prince Street Reconstruction in Bobcaygeon to Begin March 7, 2016
Home > Blog Main > Local News > Helen Street and Prince Street Reconstruction in Bobcaygeon to Begin March 7, 2016
Helen Street and Prince Street Reconstruction in Bobcaygeon to Begin March 7, 2016
Date: 02/29/2016
The project, from Front Street to Duke Street on Helen Street and from Main Street to Anne Street on Prince Street, will include full-depth road reconstruction, concrete curb, sidewalk, storm sewer, grading, and asphalt road and driveway installation.
The work, scheduled to begin next week, is phase two of a three-year project. Phase two is expected to be completed by the end of June.
The city will erect detour signs before the construction begins and motorists are asked to avoid the construction zone.
For details, please contact Corby Purdy, supervisor, infrastructure design and construction, at cpurdy@city.kawarthalakes.on.ca or call 705-324-9411, ext. 1155.